Richard McCaulley, et al, v. C L Enterprises, et al.. NE Statute of Limitation
At issue in this Nebraska Supreme Court case was whether the four year statute of limitations for construction defects under Nebraska Revised Statute 25-223 began to run on the date each contractor substantially completed its project, or on the date the entire home was completed. The court held that the limitations period against each contractor began to run upon the substantial completion of each contractor's project.
309 Neb. 141 (May 7, 2021).
Please see the original opinion for the court's exact language.
Advertisement:
Richard P. Clem is an attorney and continuing legal education (CLE) provider in Minnesota. He has been in private practice in the Twin Cities for 25 years. He has a J.D., cum laude, from Hamline University School of Law in St. Paul and a B.A. in History from the University of Minnesota. His reported cases include: Asociacion Nacional de Pescadores a Pequena Escala o Artesanales de Colombia v. Dow Quimica de Colombia, 988 F.2d 559, rehearing denied, 5 F.3d 530 (5th Cir. 1993), cert. denied, 510 U.S. 1041 (1994); LaMott v. Apple Valley Health Care Center, 465 N.W.2d 585 (Minn. Ct. App. 1991); Abo el Ela v. State, 468 N.W.2d 580 (Minn. Ct. App. 1991).
For more information about attorney Clem, please visit
his website.
For more information about his
low-cost CLE programs, please visit his CLE page.
Return to index of case
summaries
Copyright 2021, Richard P. Clem.
Attorney Richard P. Clem is responsible for the content of this page.
Richard P. Clem, Attorney
PO Box 14957
Minneapolis, MN 55414
USA
Phone: +1-612-378-7751
e-mail: clem.law@usa.net
Minnesota Attorney Registration Number 0192648
Please visit my author page at amazon.com